Notice of intent
A Notice of Intent is a formal communication typically issued by one party to another to notify them of an intention to take a specific action related to a construction contract or project. A Notice of Intent is important because it provides formal communication and documentation of a party's intentions, ensuring transparency and giving the receiving party time to prepare, respond, or take necessary actions. It also helps to protect the interests of the issuing party by complying with contractual requirements and preserving their rights under the contract.
The purpose and content of the notice can vary depending on the context in which it is used:
- A Notice of Intent to Award a Contract might be used by an employer or client to inform a contractor or supplier that they intend to award them a contract for a construction project. It is usually issued after the tendering process and serves as a preliminary indication before the formal contract is signed. The notice typically includes details about the project, the scope of work, the parties involved, and the next steps, such as contract negotiation or preparation.
- A Notice of Intent to Claim might be issued by contractors or subcontractors to inform the client or employer of their intention to submit a claim for additional costs or an extension of time due to delays, unforeseen circumstances, or changes in the scope of work. The notice outlines the basis for the claim, including the nature of the delay or disruption, the estimated additional costs or time required, and references to relevant contract clauses.
- A Notice of Intent to Terminate might be issued by either party in a construction contract if they believe there has been a breach of contract or if specific conditions warrant termination. This notice would detail the reasons for the intended termination, reference relevant contract clauses, and outline any required remedial actions or steps before the termination takes effect.
- A Notice of Intent to Begin Work might be issued bya contractor to inform the client and other stakeholders that they plan to commence work on a specified date. The notice would include the planned start date, the work to be undertaken, and any preparatory actions required from the client.
See also: Advance notice.
[edit] Related articles on Designing Buildings
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Mayors are to be given planning call in powers
Mayors across England will be able to make the most important planning decisions.
The Master Builder: William Butterfield and his times. Book review.
Why construction can't afford to ignore the skills gap.
Building Safety Regulator, 19 August
Gill Kernick appointed Independent Chair of Residents’ Panel.
Connecting knowledge, technology and conservation
Building competence for the future of built heritage.
Building Regulations and Building Safety Act
CIOB publishes free advice for non-domestic clients.
Building Safety Newsletter from MHCLG.
An extraordinary record of steel engineering worldwide.
Households living near new pylons to save on bills.
ECA warns growth must not outpace grid capacity or skills.
The role of the client and decision making
CIOB response to built environment professions call for evidence.
Construction's sustainability reporting revolution
Tracking upfront embodied carbon with digital tools.